A manager has to undertake exactly four projects-F, G, H and I in a given month subject to the following conditions: F has priority over G. H has priority over I. If one project has priority over another,the project with priority must be started earlier than the other one.There will be exactly one order in which the four projects would have to be started if it were determined that
A F has priority H
B I has priority over
C H has priority over G
D F has priority over I
Solution
Correct Answer: Option B