Direction for Question (1-4): Answer the questions on the basis of the information given below. A manager who has exactly four project --- F, G, H and I --- to undertake in a given month has made the following determinations. # F has priority over G # H has priority over I # If one project has priority over another, the project with priority must be started earlier than the other one: Q- If each of the projects takes equally long to complete, it must be true that---
সমাধান
সঠিক উত্তর: Option B