Direction for Question (1-4): Answer the questions on the basis of the information given below.  A manager who has exactly four project --- F, G, H and I --- to undertake in a given month has made the following determinations. # F has priority over G # H has priority over I # If one project has priority over another, the project with priority must be started earlier than the other one: Q- There would be exactly one order in which the four projects would have to be started if it was determined that—

A    F has priority over H

B    F has priority over I

C    H has priority over G

D    I has priority over F

Solution

Correct Answer: Option D