Direction for Question (1-4): Answer the questions on the basis of the information given below. A manager who has exactly four project --- F, G, H and I --- to undertake in a given month has made the following determinations. # F has priority over G # H has priority over I # If one project has priority over another, the project with priority must be started earlier than the other one: Q- Which of the following additional pairs of additional determinations would not conflict with the priorities initially determined?
A F has priority over H, and I has priority over F
B G has priority over H, and H has priority over F
C F has priority over I, and H has priority over G
D G has priority over H, and I has priority over F
Solution
Correct Answer: Option C