Direction for Question (1-4): Answer the questions on the basis of the information given below. A manager who has exactly four project --- F, G, H and I --- to undertake in a given month has made the following determinations. # F has priority over G # H has priority over I # If one project has priority over another, the project with priority must be started earlier than the other one: Q- Which of the following additional pairs of additional determinations would not conflict with the priorities initially determined?
সমাধান
সঠিক উত্তর: Option C