A man completes 5/8 of a job in 10 days. At this rate, how many more days will it take him to finish the job?
সমাধান
সঠিক উত্তর: Option B
5/8 of a job in 10 days 1 or full work in 8x10/5=16 days so,more days needed=(16-10)=6 days