Direction for Question (1-4): Answer the questions on the basis of the information given below. A manager who has exactly four project --- F, G, H and I --- to undertake in a given month has made the following determinations. # F has priority over G # H has priority over I # If one project has priority over another, the project with priority must be started earlier than the other one: Q- Given only the determinants above, each of the following is a possible sequence in which the four projects could be started EXCEPT—
A F, G, H, I
B F, H, G, I
C F, H, I, G
D H, F, I, G
Solution
Correct Answer: Option C