Correct Answer: Option A
Ratio of rates of working of A and B = 2 : 1
So, ratio of times taken = 1 : 2
B's 1 day's work = 1/12.
Therefore, A's 1 day's work = 1/6; (2 times of B's work)
(A + B)'s 1 day's work = (1/6 + 1/12)
= 3/12 =1/4.
So, A and B together can finish the work in 4 days.
Download our app for free and access thousands of MCQ questions with detailed solutions