A and B can do a piece of work in 12 days while A alone can do it in 20 days. How long will B alone take to finish the work?
সমাধান
সঠিক উত্তর: Option B
In 12 days, A and B can do 1 job.
In 1 day, A and B can do 1/12 job.
Again,
In 20 days, A can do 1 job
In 1 day, A can do 1/20 job
Thus, In 1 day, B alone can do (1/12 - 1/20) job
= (10-6)/120 job
= 4/120 job
= 1/30 job
Now,