A signed a contract for building a road of 1920 meters long within 120 days. He employed 160 workers for this task. But after 24 days he found that only 1/8 of the task has been finished. If A want to finish the road in time how many additional workers he has to employee ? 

A  180 

B  120 

C  160 

D  280 

Solution

Correct Answer: Option B

Solution: Days remaining = 120 - 24 = 96 

             Work done = 1920/8 = 240 meter and work remaining = 1920 - 240 = 1680 meter 

          240 meter is done in 24 days by = 160 men 

            1   "        "     "    "   1  "      "    = (160 \( \times \) 24) / 240 men. 

       1680  "         "     "   "   96 "      "     = (160 \( \times \) 24 \( \times \) 1680) / 240 \( \times \) 96  men 

                                                            = 280 men 

             Additional men need = 280 - 160 = 120 Men. 

অ্যাপ/ওয়েবসাইটে রুটিনভিত্তিক নিয়মিত লাইভ পরীক্ষা হচ্ছে।
পরীক্ষা – ৭৯
কোর্স নামঃ প্রাইমারি প্রধান শিক্ষক নিয়োগ প্রস্তুতি (২য় ব্যাচ)
টপিকসঃ
আন্তর্জাতিক বিষয়াবলী সম্পূর্ণ সিলেবাস (১০০ মার্ক)
৫ ফেব্রুয়ারি থেকে শুরু।
রুটিন দেখুন
পরীক্ষা-৫৪
কোর্স নামঃ ৫১ তম বিসিএস প্রস্ততি - ২৩৬ দিনে সম্পূর্ণ সিলিবাস।
টপিকসঃ
বাংলা সাহিত্য
খুব গুরুত্বপূর্ণঃ কাজী নজরুল ইসলাম।
গুরুত্বপূর্ণঃ মানিক বন্দ্যোপাধ্যায়, এস. ওয়াজেদ আলি, কায়কোবাদ, কাজী ইমদাদুল হক, কাজী আবদুল ওদুদ, জহির রায়হান, জাহানারা ইমাম, দ্বিজেন্দ্রলাল রায়, নির্মলেন্দু গুণ, নুরুল মোমেন, প্যারীচাঁদ মিত্র,।
কম গুরুত্বপূর্ণঃ আবুল হাসান, আসাদ চৌধুরী, আরজ আলী মাতুব্বর, আশরাফ সিদ্দিকী, আহমদ ছফা, ড. আহমদ শরীফ, আহসান হাবীব, আহমদ রফিক, ইব্রাহীম খাঁ, ঈশ্বরচন্দ্র গুপ্ত, উইলিয়াম কেরি, এম. আর. আখতার মুকুল, কাঙাল হরিনাথ, কাজী মোতাহার হোসেন, কামিনী রায়, কালিদাস রায়, কালীপ্রসন্ন ঘোষ, কালীপ্রসন্ন।
১০ ফেব্রুয়ারি, ২০২৬
রুটিন দেখুন

Practice More Questions on Our App!

Download our app for free and access thousands of MCQ questions with detailed solutions