400 person working 9 hours per day complete 1/4 th of the work in 10 days. The number of additional persons, working 8 hours per day required to complete the remaining working in 20 days is  

A  375 

B  275 

C  255 

D  345 

Solution

Correct Answer: Option B

Solution: Work done 1/4 th in 10 days. So work left 1- 1/4 = 3/4 

             1/4 th needs 10 days so 3/4 th need 30 days to complete 

     Now,  30 days need working 9 hours for = 400 persons 

               1  "       "         "        1 "        "     = 400 \( \times \) 30 \( \times \) 9 

              20 "       "         "         8 "       "      = 400 \( \times \) 30 \( \times \) 9 / 20 \( \times \) 8 

                                                                  = 675 persons 

     So, persons to be added 675 - 400 = 275   