400 person working 9 hours per day complete 1/4 th of the work in 10 days. The number of additional persons, working 8 hours per day required to complete the remaining working in 20 days is
Correct Answer: Option B
Solution: Work done 1/4 th in 10 days. So work left 1- 1/4 = 3/4
1/4 th needs 10 days so 3/4 th need 30 days to complete
Now, 30 days need working 9 hours for = 400 persons
1 " " " 1 " " = 400 \( \times \) 30 \( \times \) 9
20 " " " 8 " " = 400 \( \times \) 30 \( \times \) 9 / 20 \( \times \) 8
= 675 persons
So, persons to be added 675 - 400 = 275