A contractor estimates that he can paint a house in 5 days by using 6 men. If he actually uses only 5 men for the job how many days will it take to do this job?

A    5

B    5(1/2)

C    5(1/4)

D    6

Solution

Correct Answer: Option D

Practice More Questions on Our App!

Download our app for free and access thousands of MCQ questions with detailed solutions