A can do a job in 24 days, B in 9 days and C in 12 days. B and C together start the work but leave after 3 days. How much time was taken A to complete remaining work ? 

A  7 days 

B  9 days 

C  10 days 

D  12 days 

Solution

Correct Answer: Option C

Solution:  

                B+C can do in 1 day = \(\frac{1}{9} + \frac{1}{{12}} = \frac{{4 + 3}}{{36}} = \frac{7}{{36}}\)

                B+C can do in 3 days = \(\frac{{7 \times 3}}{{36}} = \frac{7}{{12}}\)  

              Remaining part =  \(1 - \frac{7}{{12}} = \frac{5}{{12}}\)  

             1 part is done by A = 24 day 

            5/12 part is done by A =  \(24 \times \frac{5}{{12}}\) =  10 days  