Correct Answer: Option C
B's 10 day's work = (1/15 x 10)=2/3.
Remaining work=(1- 2/3) = 1/3.
Now, 1/18 work is done by A in 1 day.
Therefore, 1/3 work is done by A in(18 x1/3)
= 6 days.