Assurance company has a project that wil take 1000 person days to complete. How many days will it take to complete the project if the company has 50 workers?

A 50

B 43

C 32

D 20

Solution

Correct Answer: Option D

1000 জন কাজটি করে 1 দিনে 1 " " " ( 1000*1 ) দিনে 50 " " " 1000/50 = 20 দিনে